GMP and/or Early Release: Commitment Approval (GMP1)

This process initiates a contract request for a Guaranteed Maximum Price (GMP) commitment in several scenarios.

  • Early Release No. 1 (CM-71, CM-MPSA-71, DB-71)
  • Amendment No. 1: Acceptance of GMP (CM-72), when no prior early releases have been issued for the commitment
  • MPSA: Construction (A-2), when no prior early releases have been issued for the commitment
  • Design-Build Acceptance of Construction Proposal: GMP (DB-72.1), when no prior early releases have been issued for the commitment
  • Execution of a Professional Services Agreement between Owner and Construction Manager (CM-10) proceeding directly to GMP, with no preconstruction services

Further Training